The City of Waco continues making significant progress on the Speegleville Road Improvement Project. To help minimize disruptions once the school year begins, construction crews are accelerating work through this phase of the project while school is out of session. We appreciate your patience as these improvements move forward.
Road Closure Schedule
- Oak Road, full closure, between Bosque Lane and Sunrise Lane Sept. 22 - Oct. 2nd
- Speegleville Road, northbound land closure, at intersection of Oak Road Sept. 28 - Oct. 18
- Speegleville Road, full closure, at intersection of Wheatland Drive Oct. 12 - Oct. 18
- Bosque Lane, full closure, between addresses 620 - 656 Oct. 26 - Nov. 15
Note: Wheatland Dr. and Bosque Ln. will not be closed at the same time.
Map Indicators
- Red: Oak Rd closure Sept. 22
- Dark Orange: Speegleville Rd Partial Closure Sept. 28
- Lt. Orange: Speegleville Rd at Wheatland Dr Oct. 12
- Yellow: Bosque Ln closure at 620-656
Additional Project Information
Any environmental documentation or studies, any maps and drawings showing the project location and design, tentative construction schedules, and other information regarding the project are on file and available for inspection by appointment only, Monday through Friday between the hours of 8 a.m. and 5 p.m.
Contact Teresa Bryant by email at teresab@wacotx.gov, or by phone (254) 750-6613 to schedule a meeting.
TxDOT Documents
The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated July 17, 2025, and executed by FHWA and TxDOT.