Engineering Services - Panther Way Re-Construction Update
Description:
Re-construction of Panther Way, from Lindenwood to Ritchie Road, approximately 4,800 feet of road.
- This will include the following utilities improvements:
- Water main (1,000 linear feet / 16" diameter pipe)
- Sanitary sewer
- Storm drain (2,500 linear feet / 18" to 36" diameter pipe)
Traffic Direction Model
Panther Way Schedule
West End:
Unpaved road surface complete in January
Sidewalk and miscellaneous work behind curb and gutter
Middle Section:
To begin following East End
Anticipated dates are April through June
East End:
Will start at Lindenwood and work west towards the first entrance of the school
Unpaved road surface complete in April
Paving on all sections is anticipated to begin in July. Please see the schedule for a more detailed project schedule.
Contacts:
City of Waco:
George Hill, Project Manager 750-6622
Terry Casper, Inspection Supervisor 750-6623
J.D. Cross, Construction Inspector 709-2464
City of Hewitt:
Bruce Braley, Community Development Director 666-6173
James Black, Public Works Director 666-2417
Kevin Reinke, Field Supervisor 733-3615
H&B Contracting:
Dustin Denard, Project Manager 848-4461
Dan Butry, Project Supt. 848-4461