Weekly Repair Schedule

Repairs for the Week of August 17, 2008

The City of Waco Street Division will be working at the following locations during the week of
August 17, 2008.

Please note that the following schedule is subject to changes.

Base Failures

  • Cottonwood Creek Golf Course
  • 20A - Daughtrey to Wood

Pothole Maintenance

  • District 4
  • Route 7

Inlet Cleaning

  • Route 11 - Franklin to I-35 - 29th to University Parks Drive

Drainage Ditch

  • Colcord to Bosque - 6th to 9th Streets

Alley/Unpaved Street Maintenance

  • 27th to 38th - Homan to Ethel

Curb and Gutter

  • Route 2 - 10th to New Road - West and Waco Drive

Concrete Construction

  • 2nd and Taylor - repair of utility cut on curb and gutter
  • Garrison and Waco Drive - repair of utility cut on curb and gutter
  • 2031 North 15th Street - repair of utility cut on street

Crack Sealing

  • Windsor - 38th to 39th
  • 19th - Cleveland to Dutton
  • Connally - Daughtrey to Bagby
  • Flint - 20th to 22nd
  • Baker Lane - Carroll to Cameron Park Drive
  • Longfellow - Tennyson to Sanger
  • Hawthorne - Kipling to Wilshire
  • Erath - 46th to Champion

Street Sweeping Routes

  • 9, 10, 12a, 12b, 13, 13a, 14
Link to Home Page News & Events link
Leadership link City Services/Departments link City Jobs link Convention & Vistors Bureau link
return to home link

City of Waco | PO Box 2570 | 300 Austin Ave. l Waco, Texas 76702
Telephone: (254) 750-5600 main
Site Design by City of Waco Graphics Department
© 2007 City of Waco. All Rights Reserved.