Park Improvements - Total: $11.6 Million
***Brazos Park East Update- March 2011***
***Video Update: Lover's Leap Ribbon Cutting Ceremony***
Brazos Park East Redevelopment
- Construction in progress
- Scheduled completion in Fall 2011
Cameron Park Renovations
- Pecan Bottoms playground completed July 2008
Phase 1 Renovations
- Construction complete on the following:
- Redwood Shelter
- Rock Shelter
- Jacob’s Ladder
- Circle Point
- Mouth of the Bosque
- Proctor Springs
- Cameron Park Clubhouse
- Wilson Creek Pedestrian Bridge
Phase 2 Renovation at Northern Gateway
- Construction in progress
- Scheduled completion Spring 2011
***Video Update: Northern Gateway Update***
Cotton Belt Trail Construction
- Construction in progress
South Waco Community Center
- Completed December 2010
***Video Update: South Waco Community Center Complete***
Hike, Bike & Walking Trails
13 Neighborhood Parks Trails: Alta Vista, Bell’s Hill, Buena Vista, Chapel, Council Acres, Crestview Gurley, Jaycee, Kendrick, Mitchell, Pioneer, Seley & Viking Hills Parks