Neighborhood Park Trails
Status as of:
April 8, 2009
Construction has begun in numerous parks. Estimated Completion Date: Summer 2009.
Oct. 16, 2008
- August 2008: Plans completed
- September 24, 2008: Construction bids opened
- October 21, 2008: Council to consider bid award
- November 2008: Construction to begin
Trail Design Plans (to view the plans, click on the name of the park)
The following parks will receive quarter-mile trails:
April 1, 2008: Schematic Plans presented to City Council
March 5, 2008: Concepts presented at Public Meeting
May 12, 2007: Voters approve $11.7 for Park Improvements
Project Description
Improvements to neighborhood pedestrian and bike trails will be taking place throughout the City of Waco. As a result of the bond election, $900,000 in new and improved trails systems will be added in 14 parks.
- One-third mile trail will be added at Trail Blazer Park in west Waco near Harris Creek Road.
The following parks will receive quarter-mile trails:
- Alta Vista, Buena Vista, Council Acres, Gurley, Mitchell, Viking Hills, Bell’s Hill, Chapel, Crestview, Jaycee and Pioneer
- Trail connections will be made to existing trails at Kendrick and Seley Parks
Estimated Timetable
- Construction to begin Winter 2008/2009
|